]po[ Earned Value Management

This package implements the Earned Value Management process (EVM, also sometimes called Earned Value Analysis or EVA) as defined in Earned Value Management (Wikipedia) . It allows users to compared planned with actual and earned costs during the life cycle of a project in a graphical and intuitive way.

image:package-earned-value-management-hours

The image above shows a typical project that is not going very well with three lines:

  • Work Planned (hours) - The work as defined in the project plan by means of a Gantt diagram or similar
  • Work Done (hours) - The work actually completed, as measured by the "percentage done" value of each task, multiplied with the planned work of that task
  • Work Logged (hours) - The hours logged by the project team while performing the work

In this example, a project manager might deduce:

  • The project is only 70% finished, even though it should be finished already
  • The project is already over budget, even though there are 30% work left to do.


Previous Versions

An older version of this package used to include the following diagram: 

Package Documentation

Procedure Files

lib/earned-value.adp        
lib/earned-value.tcl        
tcl/intranet-earned-value-management-fake-audit-procs.tcl        
tcl/intranet-earned-value-management-procs.tcl        

Procedures

im_audit_fake_history       Create project audit entries for all projects. 
im_audit_fake_history_for_project       Creates im_projects_audit entries for the project by splitting the time between start_date and end_date in $intervals pieces and calculates new im_projects_audit entries for the dates based on the information of timesheet hours and financial documents 
im_audit_project_eva_diagram_deprecated       Returns a formatted HTML text to display a timeline of dots based on Lutz Tautenhahn' "Javascript Diagram Builder", v3.3. 
im_earned_value_average_cost       Takes a list of assignees and returns the average cost per hour of these assignees. 
im_earned_value_diagram       Returns a HTML table with a list of tickets that are somehow "related" to the current ticket based on full-text similarity, configuration items, users etc. 

SQL Files

sql/postgresql/intranet-earned-value-management-create.sql        
sql/postgresql/intranet-earned-value-management-drop.sql        

Content Pages

www/
      project-eva.adp
      project-eva.tcl
 

 

  Contact Us
  Project Open Business Solutions S.L.

Calle Aprestadora 19, 12o-2a

E-08907 Hospitalet de Llobregat (Barcelona)

 Tel Europe: +34 932 202 088
 Tel US: +1 415 429 5995
 Mail: info@project-open.com