MS Project Integration - Test Cases

­ 

  ­

 Test Cases  MS Project 2003
 MS Project 2007 (32bit)
  MS Project 2007 (64bit) MS Project 2010 (64bit)

Case 1:
Check basic export functionality with start/end date  

  • Create project of type Consulting-Project in ]project-open[
  • Create two tasks (task_1, task_2)  and set start date & end date,
  • Export project
  • Load project in Desktop application
  • Check if tasks are shown correctly
   ­    
Case 2:
Does import into ]project-open[ work?

 Based on above case: 

  • Save Project in mpp format to local drive
  • Import mpp file to ]project-open[. Use the same project you have used for export 
       
Case 3:
Are changes made to start/end date in 3rd party tool correctly imported

 Based on above case: 

  • Change Start/End date of tasks in 3rd party application
  • Save Project in mpp format to local drive
  • Import mpp file to ]project-open[. Use the same project you have used for export 
  • Check if start/end date have been imported correctly
       
Case 4:
Can a task be deleted in 3rd party application

Based on above case: 

  • Delete tasks in 3rd party application
  • Save Project in mpp format to local drive
  • Import mpp file to ]project-open[. Use the same project you have used for export 
  • Check if task has been deleted
       
Case 5:
Prevent that a task is deleted in 3rd party application with logged hours assigned to

Based on above case: 

  • Log hours on a task in ]project-open[ 
  • Save Project in mpp format to local drive
  • Export project
  • Import project in desktop application
  • Delete task you logged hours on
  • Save project in 3rd party application
  • Import mpp file to ]project-open[
Expected behaviour:
A warning should appear that a task has been deleted for which hours exist in the system




Case 6:
Adding tasks in MS Project:

  • MS Project: Add task_3
  • Save as mpp
  • ]project-open[: Import mpp
Expected behaviour:
Task should be created in ]po[




Case 6 - Assigning resources in MS Project

  • Assign resource to task_3 in MS Projetc
  • Upload to ]po[
Expected behaviour:
Resource should be assigned to ]po[





Case 7:
Remove resources in MS Project

  • Remove resource from task_3 in MS Project
  • Save & upload to ]po[
Expected behaviour:
Resource should not be assigned to task 







­




Please take a moment to complete this form to help us improve our service.

Did this page help you to achieve your goal?

 Yes  No  Don't know

Please provide us with comments to improve this page:

How useful is the information?

 1  2  3  4  5
Not
useful
      Extremely
useful